Power Down
Our maintenance and network engineers are tasked with maintenance, sustainment and continual improvement of this critical network that provides time critical information to the UK armed forces.
In late 2024 the team were informed that the local site facility management services needed to shut down all power for an extended but temporary period to enable critical maintenance activities to be carried out.
The planned outage would cause loss of power to all systems, causing servers and network devices to be inactive. Subsequently, time-sensitive critical data would be affected, and our end user community would be operationally impacted.
Stage 1: Planning
Our lead system engineer formulated a multi-stage plan to ensure that all key services and data flows maintained operational throughout the power outage, and minimised downtime on minor services and peripheral devices. End users and customers that could be affected by the outage were informed in good time.
The vital change was redirecting the essential data flow to a different site through a designed redundancy pathway to ensure critical services were operational. This had to happen prior to the outage date, with enough leeway for full functionality testing.
Two teams were assembled, one for ‘power down’ and the other for ‘power up’ and procedures were devised to allow for smooth and structured operation. These procedures included a sequential order of work, system dependencies, and notes for specialised equipment.
A third team was compiled for hardware upgrade of a security appliance and a comprehensive plan was made. The three teams of onsite engineers were briefed with the procedures/plans including important details such as performing controlled shutdowns to mitigate potential issues upon power restoration.
Project Details

Stage 2: Action
Prior to the outage the critical data flow was switched to our alternate site and thoroughly tested, followed by, the day prior, all non-essential devices being powered down. The ‘Power down’ team subsequently performed the structured power down of all remaining devices, under instruction from the lead engineer.
Intermediate maintenance work was then completed in situ with facility maintenance – organising untidy cabling, removing redundant equipment, and upgrading one of our security appliances.
When the green light was given, the ‘power up’ team then commenced powering up devices in a controlled manner, running methodical system tests throughout. After confirming all devices power had been restored and the network was active, the critical data flow was switched back to site and further functionality tests were completed. The customers and end users were then informed that full system functionality had been restored.
Stage 3: Retrospectives
A meeting was held to discuss the successes during the outage and any improvements that could be made for any similar projects in the future. We received excellent feedback from our primary client and a note of thanks from the user. We were very happy to build on our reliable and effective reputation.